Embellishment and other works which should be completed by the 25th October 2010. The Valletta Business Committee will be meeting on Monday 11th 2010.
Job
|
Date
|
Duration
|
Fixing of parking at Merchants Street (monti area)
|
29-09-2010
|
1 day
|
Fixing of parking lots numbers at Merchant Street (monti Area)
|
30-09-2010
|
1 day
|
Fixing of pedestrian bollards at Merchant Street (St Christopher to Archbishop Str)
|
05-10-2010
|
4 days
|
Fixing of colour coding / numbers at Archbishop Street
|
04-10-2010
|
2 days
|
Fixing of colour coding / numbers at Merchant Street (St Christopher to Arch Street)
|
07-10-2010
|
2 days
|
Fixing of parking markers at St Christopher Street (Republic Street to Merchant Street)
|
11-10-2010
|
2 days
|
Replacing temporary bollards with permanent pedestrian bollards at Archbishop Street)
|
14-10-2010
|
2 days
|
Replacing temporary bollards with permanent bollards at Strait Street
|
18-10-2010
|
2 days
|
Fixing of permanent pedestrian bollards at St John Street (Republic to Old Bakery)
|
20-10-2010
|
4 days
|
Fixing of permanent pedestrian bollards at Melita Street (Republic to Old Bakery)
|
25-10-2010
|
4 days
|
30th September 2010
Transport Malta:
Fixing of parking markers at Merchant Street
BOVIS
Delivery plant & equipment for demolition – out of hours in accordance with CMP
Geothermal boreholes
Construction of wheel wash
Installation of vibration monitoring
Preparation for accommodation base in
Removal of trees in central reservation in the ditch
Preparation for demolition of the railway bridg
Commencement of the restoration works to opera house
Installation of OH01A accommodation.
29th September 2010
Transport Malta:
fixing of parking markers at Merchant Street
fixing of traffic signs at Merchant Street and Archbishop Street
28th September 2010
Transport Malta:
Fixing of parking markers at Merchant Street
BOVIS
Installation of vibration monitoring equipment in yellow garage
Installation of the wheel wash in the ditch
Opera House scaffolding erection
Geothermal boreholes drilling