An additional rain water culvert is to pass parallel to the existing one as this is not capable to cater for the increase in run off storm water in the surrounding roads.
Works have commenced this week and will be divided into four phases. No road closures would be required, however on street parking would be removed in stretch were works are being carried out.
Duration of works is planned to take one and a half months. All access to commercial outlets and residents (including garages) will remain accessible.